COMPANY HEALTH AND SAFETY POLICY

TABLE OF CONTENTS

Page

1. Introduction ———————————————————3

2. Policy ——————————————————————4

3. Responsibilities —————————————————–5

4. Security and Traffic Regulation ———————————-7

5. Welfare —————————————————————8

6. First Aid —————————————————————8

7. Waste Management and Disposal—————————– 8

8. Emergency Procedures ——————————————-9

9. Evacuation ———————————————————–9

10. Accident Investigation and Reporting ———————–9

11. Safety and Training ———————————————10

12. Hazard Identification and Risk Assessment ————–10

13. Unusual Weather ———————————————–11

14. Buried (Underground) Services—————————– 11

15. Cartridge Operated Fixing Tools —————————–12

16. Compressed Air ————————————————–13

17. Hand Tools ——————————————————–13

18. Power Tools ——————————————————-14

19. Welding and Cutting——————————————– 14

20. Lifting Operation ————————————————-15

21. Plant and Equipment——————————————– 17

22. Electricity———————————————————- 17

23. Excavation ———————————————————18

24. Fire Prevention————————————————— 19

25. Housekeeping ————————————————-19

26. Scaffolding and Work at Height —————————20

27. Ladders———————————————————- 21

28. Mobile Work Platform————————————— 21

29. Permit to Work System————————————– 22

30. Personal Protective Equipment—————————- 23

31. Winch Work—————————————————– 25

32. Pre-Commissioning ——————————————–25

1.0 INTRODUCTION

This health and safety plan has been prepared to provide the basic rules and procedures necessary

to avoid injury to our employees and damage to equipment and materials. Safe attitude is the key

factor in accident prevention. We at Ok Hat Group all employees to develop a

positive and continuing concern for safety both on and off the job by making safety a matter of

personal commitment.

Every attempt shall be made to comply with the specification and strict quality control as per

site regulations and Ok Hat Group ‘s health, safety and environment manual and quality

plan for electrical work.

2.0 POLICY

Policy Statement

It is the policy of Ok Hat Group to provide, maintain and improve as far as possible

safety, health and environmental conditions of its operating sites, to instill in every employee

safe working habits and attitudes and provide the necessary training and awareness of rules

and discipline for safe working conditions on the job. In all instances Ampere Engineering

Safety Procedure and Safety standards will meet legal requirements.

3.0 RESPONSIBILITIES

3.1 Project Manager

a. Shall assume full responsibility of safety performance of the project site according to the

health, safety and environmental plan and contractual requirements with the assistance

of the safety officer and all supervisory personnel.

b. Plan the site health and safety plan and monitor implementation of the same.

c. Perform and co-ordinate construction work in the safest manner.

d. Establish a code of disciplinary action necessary to develop an efficient functioning of

the safety program.

e. Ensure that a full risk assessment is undertaken and provide instructions to establish

working methods to explain the sequence of operation to outline potential hazards at

each stage and indicate precautions to be adopted.

f. Request his supervisors to take immediate corrective action, if he discovers any unsafe

acts or conditions.

g. Inspect the entire work area at least once a day to ensure that all operations are being

conducted in a safe manner.

3.2 Safety Officer

The safety officer shall

a. Ensure that the safety rules are adhered, by all site personnel and visitors.

b. Implement the safety rules where necessary.

c. Carryout work site surveys on daily and weekly basis.

d. Inspect tools and protection equipment arriving on site prior to issue.

e. Record and analyze accidents, injuries and damages as and when they occur.

f. Ensure that healthy work conditions are maintained.

g. Prepare and issue safety reports as and when required.

h. Conduct safety and maintain records of safety induction training of the new workers

arriving on site and in advance of their field assignments at work site.

3.3 Site Supervisor

Site Responsibilities

a. Be familiar with those parts of the schedule applicable to the work on which sub-ordinate

workers are engaged.

b. Incorporate safety procedures into routine tasks and see that they are obeyed (Pre task

safety instructions).

c. Conduct daily safety meetings with the sub-ordinates and records to be maintained.

d. Conduct daily worksite inspections to identify and correct any unsafe acts or conditions

promptly when they are observed.

e. Ensure that their subordinates are trained to carry out specific works with the appropriate

safety precautions.

f. Ensure that new employees are properly instructed on precautions to be taken before

they are allowed to start work.

g. Report accidents, unsafe conditions and defects in equipment to the safety officer

h. Set a personal example to the subordinates.

3.4 ALL EMPLOYEES

SAFETY RESPONSIBILITIES

a. All employees of Ok Hat Group, its subcontractors and or others shall undertake

to abide by the safety regulations either stipulated in the manual or specially enforced on

certain occasions by Project Site Manager.

b. Use the correct tools and equipment for each job. Use personal protective equipment as

required and provided.

c. Do nothing to endanger themselves or fellow employees.

d. Keep tools and equipment in good condition / inspect tools equipment for defects

immediately to a supervisor / foreman.

e. Report any accidents, near misses or hazardous conditions to a supervisor/foreman.

f. Obey all posted warning signs and barricades.

g. Follow instructions from supervisor, if in doubt ask questions. Never commence work

without a work permit, if a permit to work system exists.

h. Cooperate with safety officer who is on the job for everyone’s safety.

i. Know emergency procedures (siren codes, assembly points, wind socks etc.)

j. Disciplinary action will be taken against violations of any safety rules which will be

decided by the Project Manager.

4.0 SECURITY AND TRAFFIC REGULATIONS

a. Movement of all personnel/materials/plants/equipment is to be controlled by gate pass.

b. Smoking in the sites is strictly prohibited where “NO SMOKING” signs are provided

c. Drivers and operators shall fully comply with all local traffic laws, traffic regulations, controls

and signs.

d. The maximum speed limits on the site roads are to be strictly followed.

e. Strict disciplinary actions will be taken against person who will violate traffic laws

f. Vehicles and equipment shall be properly parked where they do not block access or

emergency routes. Ignition keys shall be left with ignition switch of temporarily parked

vehicles.

g. Personnel shall not be transported “standing up” in pick up trucks etc.

5.0 WELFARE

Welfare facilities provided by Ok Hat Group must be maintained and kept in good

conditions.

a. Eating area must be kept clean. Empty cartons and packages must be placed in bins

provided.

b. Toilet and washing facilities must not be misused. They will be cleaned, sanitized and

serviced daily.

c. Rest areas must be kept clean and tidy.

d. Site offices/ cabins must be kept clean, waste paper / materials must be removed daily.

7.0 FIRST AID

First aid treatment for any injury, burns, electric shock and other accidents will be done

according to the guideline of Ok Hat Group and DUBAL / SNC.

8.0 WASTE MANAGEMENT AND DISPOSAL

a. Waste Management shall comply with CLIENT’S waste management plan.

b. Material shall be stored in an orderly and safe manner and disposed according to the rules.

c. Frequency of waste removals will be based on job site conditions.

d. Disposal by burning of any waste material at the job site will be prohibited without a prior

written approval.

e. Garbage containers will be kept clean and emptied when full.

f. The safety officer will regularly inspect storage facilities.

g. Hazardous and Non Hazardous waste will be disposed separately according to the

conditions.

9.0 EMERGENCY PROCEDURE S

 Emergency on site may occur due to a major fire incident / accident involving heavy machinery

in the plant / yard, explosion, gas leakage, structure collapse etc. During an emergency go to

the nearest office, which has a telephone, or use any mobile phone available and inform about

the incident / accident to the concerned authorities.

Procedure during an emergency will be placed everywhere at the site and offices.

Personnel to be approached in the event of an emergency are as follows with their respective

contact numbers:

 Ok Hat Group:

1. Project Director Hatim Hasimi 00905399338404

2. Project Manager Abdul Rahman Hasimi 00905551722227

 3. Safety Officer Abdul Malik Hasimi 00905555561686

 CLIENT : as required.

9.0 EVACUATION

During occurrence of a serious incident / situation which require the site to be cleared of all

personnel, all management and supervisory staff shall instruct their subordinates to leave their

work areas and proceed to the “ assembly point “ made for this purpose and wait for “roll call”

and further instructions.

10.0 ACCIDENT INVESTIGATION AND REPORTING

An accident is an unplanned event which may or may not, result in injury or damage. It is

important to ensure that every accident is investigated to the extent necessary to determine the

cause of it. Only by this means it will be possible to ensure appropriate control measures can

be put in place to prevent a re-occurrence.

The Project Manager as part of their overall site safety plan, must ensure arrangement are in

place and nominated staff trained to undertake the accident investigations to suit the particular

circumstances of the project.

Any incident that has a potential for a loss to the company, which includes injury, property

damage, fire, production delays etc or any incident that could lead to any of the above, shall be

thoroughly investigated.

The frontline supervisor has the most to gain from the investigations and also has the greatest

knowledge of the area and the people and is, therefore, the ideal person to carryout the

investigation. It should enable him to obtain the information required to make recommendations

and take actions to prevent re-occurrence.

Incident report format, report of accident involving injury and lost time injury records / monthly

accident reports are attached. Ok Hat Group / Clients formats shall be used to report

such incidents. (Refer: Annexure “A’” for Ok Hat Group ‘s format).

11.0 SAFETY TRAINING

Safety training, Induction training, toolbox talks, in housing training of different activities will be

given to the supervisors and workforce according to the safety regulations of Ok Hat Group

12.0 HAZARD IDENTIFICATION AND RISK ASSESSMENT

Prior to each task or job commencing a study of the work will be conducted. This study will

incorporate Hazard identification, Risk assessment and job safety. The decisions made during

the study will form the basis for the job safety plan.

Each task, where pre-task planning is required, will be the subject of the study. This will be

carried out by the engineer or supervisor in charge of the work. His study will incorporate all

recognized hazards and degree of risk associated with each one.

A risk assessment will be carried out for each identified hazards. Risks can be graded

similarly.

 a. Those with high probability of occurrence.

b. Those with medium probability of occurrence.

 c. Those with a low probability of occurrence.

A form of Risk assessment has been provided. Information provided gathered during these

assessment will be entered into a job safety plan.

Prior to work commencing details contained in the job safety plan will be passed to the

workforce through toolbox talks and “stand-up” meetings.

13.0 UNUSUAL WEATHER

In order to protect and minimize loses from unusual weather (flood, heavy rain storm, typhoon,

earthquake etc) Ok Hat Group and its subcontractors will follow the guidelines from

concerned Clients authorities.

A standard for work suspension will be established by taking consideration the site conditions

and the type of work.

After any unusual weather condition the emergency crew will carryout thorough inspection of

the site and prepare a report to the Project Manager detailing damage to any permanent or

temporary structures, plant, scaffolding, ladders or access that may adversely affect safety.

14.0 BURIED (UNDERGROUND SERVICES)

Majority of accidents involving buried services are caused by failure to locate position of cables

and pipes before excavation or by subsequent failure to take all practical precautions while

excavation is in progress. It is therefore essential that a safe system of work is laid down and

implemented.

The most common buried services are:

a. Fire water main

b. High and Low voltage electrical supply cables.

c. Drains / Sewers

d. Pipelines (Oil & gas)

e. Telecommunication lines

As a control procedure the following shall be adopted.

a. Concerned Clients’ authority to be informed before any excavation work or movement of

heavy plant / equipment.

b. Permit to work procedure will be strictly enforced for excavation / ground penetration with in

the specified area.

15.0 CARTRIDGE OPERATED FIXING TOOLS

Cartridge operated fixing tools can be extremely dangerous if not used correctly, as they are

very similar to fire arms. Persons who need to use these tools must be properly trained in

their safe use and handling procedure before using these type of tools.

A standard control procedure to be followed for cartridge operated tools are as detailed below:

a. Proforma for issue / return record.

i) Date / time tool was issued / returned.

 ii) Serial number of tool

iii) Quality of Cartridge issued and color.

iv) Quantity of “LIVE” / spent cartridges returned and color.

v) Name / ID number of operator.

Location and details of safe / lockable storage facility and a complete list of trained operators

(Name and ID number) are to be maintained.

Check operators handling the tools for the following:

a. Tools are not being loaded until required firing time.

b. Tools and cartridges are not being left unattended.

c. Hands are being kept well clear of the open ended barrel / firing points.

d. Tools are not pointed towards other workers / work area.

All cartridge operated fixing tools are subject to formal inspections, prior to being used on site

and every month thereafter and written records to be maintained.

16.0 COMPRESSED AIR

Compressed air may be used for operating pneumatic tools and equipments. Before any

pneumatic equipment is installed or pneumatic tools prepared for use, the manufacturer’s

instructions shall be read and fully understood.

Pneumatic tools and equipment shall not be used for any purpose other than that for which

they were designed. Non-standard attachments and accessories shall not be used.

The compressed air supply must be regulated to the correct pressure, adequately filtered,

dried and where necessary lubricated.

The means of disconnection from the air supply must be accessible.

Safety goggles and breathing mask shall be worn where grit or dust maybe produced or

disturbed. Ear protectors shall be worn where the work generates high noise levels in excess

of 85dB. In no circumstances should compressed air be directed at any part of a person’s

body. Precautions must be taken to prevent clothing, hair, rags etc from becoming entangled

with moving parts.

Safety mechanisms shall not be tampered with or disabled.

Only hoses and couplings of the recommended size and rating shall be used, they shall also

be in good condition. All coupling shall be wired to prevent their parting. Leaking hoses shall

be removed from work areas.

17.0 HAND TOOLS

Portable tools

The use of portable hand / power tools can present a hazard; both from direct injury to

personnel and as a potential source of ignition.

Common sources of accidents are:-

Use of inferior or improperly maintained tools, e.g.; hammers with loose heads, blunt chisels,

and electric tools with faulty wiring or faulty insulations. Improper use of tools e.g.; use of

screwdrivers as crowbar, or length of pipe as an extra lever for a spanner.

Supervisors and Safety officer must inspect the site on a regular basis and ensure that only

good quality hand tools are being used.

Individuals using portable tools must use them only for the purpose for which they are

designed. It should be kept in a safe working condition. Defective tools must not be used and

it must be kept clean and frequently

Checked and well maintained. Defective parts must be replaced and cutting edges must be

kept sharp. Keep them in a safe condition during work break and return them after use to the

designated storage place and carry them in a safe manner.

18.0 POWER TOOLS

Power tools are usually powered by electricity or compressed air. Air powered tools are

preferred for hazardous areas in all cases when the power output from the tools is sufficient

for the job. Use of explosive cartridge equipment is subject to special restrictions beyond

what is specified in the hot work permit and must be approved by the operating supervisor.

Power tools must be operated in accordance with basic electrical safety requirements. They

must be suitable for the hazard classification of the area in which they are used or agreed as

acceptable prior to issue of the permit to work. These tools are not to be used when there is

any detectable flammable gas in the area. They must be fitted with appropriate guards

around the moving parts & protected against damage from dirt, oil water etc.

Personnel using power tools must operate the tools in a safe manner, e.g.; using a “starter”

mark when drilling, avoiding violent striking of abrasive wheels, using protective screens as

appropriated. Ensure that the work piece is properly secured, and not liable to move or cause

injury from falling off cuts. Wear appropriate protections.

19.0 WELDING AND CUTTING

All welding and cutting apparatus shall be inspected daily. Defective apparatus and

equipment shall be replaced or repaired. Combustible materials, equipments such as gas

cylinders, rubber hoses, and debris shall be removed or shielded from heat, sparks and slag

from welding and cutting. Welding and cutting work at elevated places shall be conducted only

under safe conditions; a safety belt shall be worn.

Welding and cutting in an area where flammable vapors be present shall be inspected by the

Client’s safety engineers for safety and gas done prior to start of work.

When welding or cutting in confined areas for a long time, the space shall be sufficiently

ventilated. During the work the concentration of oxygen in the air must be more than 18

percent. When working in confined area, the workers should at least be paired to avoid

accidents, with one worker in clear sight out of the other.

Welding machines shall be placed 15 centimeters above the ground to keep them dry.

Welding machines shall be placed and secured with a suitable wedge to keep them in a

horizontal position. An electrical welding machine shall be effectively grounded. All other safe

practices will be followed as mentioned in the safety regulations of Ok Hat Group.

Principal Hazards are:

a. Leakage of flammable, toxic or inert gases particularly in confined spaces.

b. Leakage of oxygen to produce oxygen enrichment in confined spaces with the consequent

risk of rapid and fierce combustion.

c. Explosions due to oxygen contact with greases and oils.

d. Fire exposure, leading to cylinders failure in the form of violent explosion, failure of hoses

or other fittings.

20.0 LIFTING OPERATIONS

20.1 USE OF MOBILE CRANES

All cranes shall have current test certificates and be operated only by qualified

personnel. The following precautions must be taken while operating cranes.

a. Carryout routine daily checks for obstructions, conditions and cleanliness.

b. Ensure that correct capacity chart is used and never overload the crane.

c. Do not swing the machine, unless the area around the machine is clear.

d. Do not leave the machine unattended, while the engine is in motion.

e. Never leave the machine without the operator while a load is suspended (where

applicable barricade areas during lifting operations)

f. Never lift suspended load over people.

g. Tag lines of sufficient length shall be used to guide suspended loads.

h. Banks man must be trained and use standard / international signals when giving

directions.

i. They must wear reflective vests for easy identifications and crane should not be

operated without a banks man.

j. The out riggers of the crane shall be fully extended and spreader pads to be placed

beneath them.

k. No personnel other than authorized operators shall ride on moving cranes, forklifts

or any other lifting gears.

The crane shall be retested by an independent approved, examination authority after all

major alteration or repair. Crane shall not be operated near any overhead power line,

unless it is necessary, the power should be switched off for the duration of the lifting

operation. No hoisting, lowering, swinging or traveling shall be done, while somebody is

on the load or hook.

The crane shall be fitted with following safety devices:

a. Safe load indicator giving warning to driver as the safe load limit approached.

b. A device giving clear audible warning when the crane is reversing or tracking.

c. Over boom and over hoist cut out.

At the end of work, the cranes must be stopped and shut down by qualified personnel,

boom down to 45o with swing brakes applied. Load must be removed from the hook

and the hook must be raised to the highest operation point.

All types of other lifting operations will be followed according to Ampere Engineering’s

guidelines.

21.0 PLANT AND EQUIPMENT

Plant and Equipment covers a wide variety of different items and construction machinery,

which can generally be divided into two categories.

(Plant) mobile – Self-propelled

(Equipment) static – Has to be placed in position

In all cases, each item of plant or equipment has its own manufacturer’s recommendations for

safe use and often has legal / statutory requirements for inspection, testing and certification.

The plants / equipments used in this site shall be in accordance with site regulations of Client.

22.0 ELECTRICITY

Electrical energy is used extensively to assist in the construction process. It is found that

electrical shock is a regular cause of death on construction site.

The common causes of this type of incidents are:

a. Damaged or faulty equipment.

b. Poor insulation.

c. Inadequate ear thing method.

d. Not following procedures for isolating.

e. Persons working too close to live services.

f. Excavation works

g. Unauthorized / Untrained people.

Only qualified electricians will be permitted to energize / isolate electrical supplies. Work in

live plant / operational areas and on new permanent installations will be covered by the permit

to work system, which will include an electrical permit and the Lock out / Tag out system.

Equipments will be inspected and tested and during these procedures if items are found to be

faulty they will be removed from service immediately. If they cannot be repaired they will be

removed from the site.

All wiring will be insulated and where there is a possibility of physical damage the wiring must

be further protected by metal conduits or use of armored cables. Insulation shall be provided

at all locations where it is possible for workers to come into contact with live equipments.

Earth cables will be tested for continuity and resistance to ensure that they are effective for

that particular application. Remedial actions will be taken where they are found inadequate or

ineffective.

Isolation procedures detailed as a part of the permit to work system. Isolations are intended to

prevent accidental contact with live electrical equipment. Work cannot officially be carried out

on electrical systems until a competent person has indicated, in writing, on a work permit, that

he has isolated the system by means of locks, using the lockout / tag out procedure.

All electrical systems shall be labeled accordingly. Work adjacent to electrical systems shall

be subject to work permit procedure. All safety procedure mentioned in the site regulations

will be followed while working near the overhead power lines and during excavations.

23.0 EXCAVATION

All site regulations such as PTW will be followed while excavating the area where

underground services present.

The following general safety requirements also will be fulfilled at the time of excavation even

in “green fields”.

a. All excavations exceeding a depth of 1.2 meter must be shored, benched or sloped to

prevent cave in.

b. Shoring must be kept at least 30 cms. Above the top of excavation.

c. Soil must be kept at least one meter from the edge of the excavation.

d. Vehicles, equipment and materials must not be positioned or driven near to the

excavation, where they may cause the excavation to collapse.

e. All excavations barricaded to prevent persons from falling into them and at night flashing

lights to be provided especially in the access ways.

f. During excavation works, if underground utilities marker tiles or identification tape markers

are exposed, all excavation works will be

g. Immediately stopped and the site supervisor will inform the concerned CLIENT’S

personnel.

h. A means of safe access and egress shall be maintained for all excavations more than 1.2

meter depth.

i. Gas checks will be necessary if the excavation is classed a confined space.

j. If the excavation is classed as a confined space, regulations governing confined space

entry will apply.

24.0 FIRE PREVENTION

Fire prevention means taking necessary action to prevent fire and explosion. One of the most

important parts of any job plan is to totally eliminate the potential of accidental fire and

explosion, by which a major hazard is eliminated. This prevents injury to workmen, damage

or loss of property.

Ok Hat Group will provide sufficient fire extinguishers at the offices and site premises.

These fire extinguishers will be inspected and signed monthly. Damaged extinguishers shall

be replaced and discharged one refilled accordingly. Work force shall be trained to operate

the fire extinguishers and other emergency procedures during fire. The use of any fire

extinguishers must be immediately reported to safety department. Storage of flammable

liquids and combustible materials will be done in accordance with the guideline given in the

site regulations.

25.0 HOUSE KEEPING

Good housekeeping is a very important part of accident prevention. A clear and well￾organized work area shows that the workers have a good attitude and go about their work in a

professional manner. Good house keeping prevents fire hazards.

Ampere Engineering supervision will ensure that the site and work areas are maintained to a

high standard of housekeeping at all times.

To achieve good housekeeping the following general requirements are to be maintained.

a. Clear access shall be maintained to emergency exits and escape routes at all times.

b. Clear access shall be maintained to first aid facilities, fire fighting equipments, alarm

points, electric panels and ladders.

c.When not in use, materials, tools and equipments shall be properly stored “ a place for

everything and everything in its place”

d. Electric cords, air hoses and cutting torch hoses shall not be placed where they create a

tripping hazards causing injury.

e. Liquid spills must be cleaned up immediately. Contaminated soil or sand shall be

managed as waste.

f. Rubbish shall be removed from the work site as required.

g. Suitable skips / bins will be provided for general site debris and emptied as required.

h. Soiled / rags shall be kept in approved containers separate from clean rags.

26.0 SCAFFOLDING AND WORK AT HEIGHT

a. Scaffolding shall be erected in accordance with the good practice and safety

regulations.

 b. Beyond 2 meters height, they shall be fitted with adequate hand rails, ladders and

toe boards as well as other security devices such as tying of ropes / chains to

prevent people and or tools from falling.

c. The stability of the construction of scaffolding shall be checked, on the ground, on the

structure and between components of scaffolding. Scaffolding shall be braced and

secured for stability.

d. The stability of the construction of scaffolding shall be checked, on the ground, on the

structure and between components of scaffolding. Scaffolding shall be braced and

secured for stability.

e. The wooden planks which are used for making scaffolding shall have a minimum

thickness of 38 mm and tied / secured firmly to the scaffolding.

f. All scaffold structures shall be erected with approved components.

g. Scaffolding shall be designed, erected, altered and dismantled only by experienced

workmen under the direction of a competent supervisor.

i. Scaffolds shall be inspected weekly intervals by the authorized scaffold inspector who

shall sign & date the “scafftag” after each inspection. Scaffolding not considered safe

should have the “scafftag” withdrawn & a prominent “DO NOT USE” sign displayed.

j. Each and every scaffold erected, regardless of duration of use, shall comply with

Ok Hat Group / CLIENT/S requirements.

27.0 LADDERS

Ladder must always be used as a means of access and not as a working platform.

The following general requirements needed while erecting a ladder.

a. All ladders shall be an “approved” type.

b. Access ladders to working platforms shall be firmly secured at the landing. The ladder

must extend at least 1 meter above the landing.

c. Ladders shall be set up a safe climbing angle. The distance between the base of ladder

and supporting structure will be one quarter of its extended height.

d. Long ladders may require additional securing to prevent swaying or sagging.

e. Ladder shall be set on a firm and level footing.

f. When step ladders are used, the user shall not climb above the second step from the top

of the ladder, nor shall be use the step – ladder top, braces, back section as a seat or for

climbing.

g. Access points to ladders shall be kept free of obstruction.

h. Approved non-conductive ladders will be used for working on or near to live electrical

wiring & equipment.

i. Damaged or deformed ladders shall be destroyed.

28.0 MOBILE WORK PLATFORM

Mobile work platform are designed to lift workmen and light tool to elevated work places.

Mobile work platforms that are properly maintained and operated provide a safe means of

performing work at heights.

Before using mobile work platform the following general safety requirements are

recommended.

a. Mobile work platform operators must be trained and certified by an approved authority

(usually the manufacturer or hired company).

b. Each mobile work platform shall be marked with its safe working load (SWL) and

maximum number of persons that may be lifted.

c. All Controls, switches, levers and buttons shall be clearly marked showing their functions

and method of operation and be clearly visible to the operator.

d. The floor of the work platform shall be of a non – slip surface and be designed to allow

water drainage.

e. All sides of the work platform shall be enclosed by a top guard 1 meter height include an

intermediate guard rail at an equal distance between the platform and top rail. All sides

must be enclosed by a toe board not less than 15 centimeters high.

f. Control levers and buttons shall be of a design that prevents accidental operation.

g. A safety harness, safety belt shall be worn at all times by each person in the work

platform. The lanyard shall be attached to a secure anchor point.

h. Personnel shall not lean out of work platforms and safety helmet with chinstrap shall be

worn by each person in the work platform. Ok Hat Group will use this type of

platform, if required with all safety precautions in hand.

29.0 PERMIT TO WORK SYSTEM

The objective of the permit to work system is to ensure that written permission and

authorization is given to carryout the defined work that is potentially hazardous and that all

possible measures are taken to maintain the safety of personnel and equipment in all areas of

operations. Ok Hat Group personnel will fully comply with these procedures.

The purpose of these regulations is to set down a system for the safe control of work, which is

as follows:

a. Provides for maximum safety of both personnel and plant.

b. Provides for good coordination between operation and maintenance work.

The permit to work system serves the following functions:

a. Prescribes the nature and extent of the work to be conducted.

b. Prescribes the conditions (isolations requirements) that have to be observed.

c. Records the places in which men other than operating personnel are, for a specific time.

d. Gives written permission for work to be done.

e. Brings to the attention of all parties the steps that have been taken and must be

maintained to make the plant / area safe for work to be done.

f. Details of any remaining hazards and precautions to be taken.

g. The standard CLIENT permit to work form for contractors shall be used for all works.

30.0 PERSONAL PROTECTIVEEQUIPMENT

30.1 Protective Clothing

a. The supervisor must issue each employee with necessary protective clothing (with

Ok Hat Group Logo) when required and ensure that protective clothing is kept

relatively clean by the employee.

b. Any piece of clothing becoming contaminated with any kind of flammable liquid must

be removed at once.

c. Supervisor/foreman must ensure that the personnel are aware of the correct usage of

the specified clothing/equipment for specific tasks.

d. It is forbidden to work stripped to waist and or wear shorts.

30.2 Helmet

a. The wearing of a helmet is compulsory on site at all times.

b. The safety helmets must be of approved type conforming to EN 397 or equivalent

acceptable by client.

30.3 Safety shoes

The wearing of safety shoes is compulsory. The safety shoes shall be conforming to BS

1870 and / or equivalent.

30.4 Protective gloves

a. The wearing of gloves is recommended for protection against chemical, physical and

biological hazards.

b. Cotton hand gloves should be worn while rigging.

c. Leather hand gloves should be worn while welding cutting and burning.

d. Special high insulation hand gloves to be worn by electricians, while working on HV/LV

lines.

e. All gloves shall be of approved industrial standard.

30.5 Eye / Face Protection

a. The wearing of eye / face protection is compulsory while grinding, welding and cutting

etc. where flying sparks / objects may cause damage to the eyes.

b. Wearing of clear safety spectacles is compulsory inside the building all times.

c. Wearing of eye / face shields is compulsory for:

i) Welding

ii) Grinding

iii) Chipping, Hammering and shearing at any location.

iv) Assisting sand / grit blasting operations

v) Cutting and burning (tinted)

Ear protection, respiratory protective equipment, and full body safety harness with double lanyard to

be worn as and when the safety situation arises.

31.0 WINCH WORK

The winch work shall be used for 11/33/132kV cable pulling purposes. Winch shall be installed

on a firm ground with a good view for the work. The area where the winch is installed shall

have ample space for inspection and maintenance and be kept clean at all times.

The winch shall be installed securely to prevent floating, slipping and vibrating. Foot brakes

shall be provided with adequate spacing from the ground to permit the brakes to be operated

freely. Gears shall be provided with cover and winch motor shall be grounded. The winch

operator shall not leave his position during winch operation.

32.0 PRE – COMMISSIONING

During Pre–Commissioning and commissioning requires strict compliance to safe working

practices and standards, which have already been applied during the construction stage. It

also requires a state of mind that combines a sense of awareness with critical examinations of

every act and situations for unsafe consequences.

Prior to the commencement of pre-commissioning and commissioning, all procedures are required

by DUBAL / SNC; e.g.; safety clearance etc. shall be followed.